OT Backup Before a Configuration Change: What to Check for PLCs, HMIs, and SCADA Systems

Any changes to the PLC program, HMI design, or communication settings should have a clear point of reference. Before the team begins work, it must know what state of the installation it considers to be the current one and what files will be needed to identify or reproduce that state.

OT Backup Before a Configuration Change: What to Check for PLCs, HMIs, and SCADA Systems

Any changes to the PLC program, HMI design, or communication settings should have a clear point of reference. Before the team begins work, it must know what state of the installation it considers to be the current one and what files will be needed to identify or reproduce that state.

The general rule of making a backup before making a significant change, including a configuration change, is outlined in the material Data Backups on the Cyfrowy Biznes Website. In OT, a single project export is often not enough. NIST lists, among other things, program and logic files, configurations, I/O lists, firmware, HMI graphics, license keys, vendor tools, documentation, and system and virtual machine images NIST SP 1339, OT Backup Quick Start Guide

The following material pertains to preparing backups of artifacts prior to a planned change. It does not specify backup frequency, retention periods, storage media, RPO, or RTO. Nor is it a guide for restoring the system in a production environment. Such decisions require an analysis of the specific installation, process, and responsibilities within the facility.

A PLC backup is more than just a program file

The term “PLC backup” can mean several different things: a source project in an engineering environment, a readout from the device, hardware configuration, communication settings, or an archive containing some of these elements. The files may be related to one another, but they are not interchangeable.

Before making a change, it’s best to ask what the team wants to be able to identify, verify, or reproduce later. The scope of the copy depends on that answer.

For the PLC, it is a good idea to set the following:

  • which project serves as a reference point;
  • whether it matches what is implemented in the driver;
  • Which hardware and communication configurations are stored separately;
  • Does the project include all device-specific data?;
  • Who can confirm that the file is compatible with a specific driver and installation version?;
  • the change associated with the archive.

NIST lists program, logic, and configuration files as examples of elements needed to recreate an OT environment. This list must be adapted to the technology and scope of the planned work. NIST SP 1339

A file on its own, without any information about its origin, may be useless. Names such as “final,” “new,” or “backup_ok” do not indicate which device the copy came from or what state it describes.

HMI and SCADA: Application design does not always cover the entire environment

In the case of HMI or SCADA systems, the application design must be separated from the environment in which it runs. NIST lists HMI graphics files, software supporting redeployment, and system or virtual machine images among the elements that may be needed for recovery. This does not mean that every station requires a system image. The scope depends on the architecture and deployment method. NIST SP 1339

Before making the change, it's a good idea to check:

  • where the project is located and whether it can be unambiguously assigned to an application;
  • What configurations are stored outside the project;
  • Does a specific version of the tool need to be used to open, edit, or deploy the file?;
  • Does the project depend on libraries, drivers, services, or other components?;
  • Does the backup include only the application data, or does it also include the system environment?

CISA in the #StopRansomware guide It mentions maintaining up-to-date images of critical systems and verifying the availability and integrity of the copies. This is a general recommendation regarding ransomware resilience, not a requirement to create an image of every OT system.

I/O lists, firmware, tools, and licenses

NIST also takes into account I/O lists, firmware, license keys, and the vendor's configuration tools. Each of these categories is relevant only when it relates to a specific device or a planned change. NIST SP 1339

The team should determine, among other things:

  • Does the change affect the configuration of the inputs and outputs?;
  • Does the project depend on the firmware version?;
  • What tool can be used to open and verify the file;
  • Is the information needed for the legal and technical use of the software available?;
  • Who is responsible for access to these resources?

Not every element needs to be copied with every change. However, you must confirm that omitting it is a deliberate decision and not an oversight.

The documentation preserves the context of the copy

NIST lists support documentation among the elements that may be needed for reconstruction. The proposed change primarily concerns documents that enable the interpretation of files: scope descriptions, schematics, signal lists, device references, protocols, and identification of the technical owner. NIST SP 1339

There’s no need to organize all of the facility’s documentation. It’s enough to identify which materials are necessary for this change and this set of artifacts. If a diagram, I/O list, or version confirmation is missing, record it as an open issue.

A copy is valuable when it can be incorporated into the system's history. NIST links backup management to the current inventory, asset criticality, and the change management process. NIST SP 1339

A simple working notation may include:

  • device or application ID;
  • description of the artifact;
  • date of acquisition;
  • the status and version to which the copy refers;
  • the number or description of the planned change;
  • storage location;
  • the person who collected the file;
  • a person who confirmed its intended use;
  • list of items not included in the copy;
  • verification status.

This is an organizational proposal, not a NIST minimum standard. Its purpose is to distinguish between several states that are often confused:

  • "located" means that the file's location is known;
  • "downloaded" means that a copy has been created or obtained;
  • “identified” means that it has been associated with a device and a scope;
  • “Verified” means that the agreed-upon inspection has been performed.

None of these statuses, on its own, confirms that the system can be fully restored.

Verifying a copy without risk to production

The mere existence of a file does not prove that it can be used. CISA's Recommendations for ICS Systems It emphasizes the importance of backing up data and configurations, as well as testing backups and recovery processes. The Cyfrowy Biznes article also recommends verifying that files can be restored from the backup.

NIST describes repeatable playback tests on non-production systems. These tests are intended to evaluate the reliability of the storage medium, practice procedures, and verify the functional integrity of the restored system. NIST SP 1339

The scope of the audit should be clearly stated. The following may be reviewed:

  1. whether the file exists and can be read;
  2. Does it open in the correct tool?;
  3. Does the set include all the agreed-upon artifacts?;
  4. Are the artifacts associated with the correct device and version?;
  5. Can the agreed-upon functional test be conducted in a secure, non-production environment?

Each level addresses a different question. Opening a file is not a functional test, and testing a single artifact does not prove that the entire environment can be reproduced.

NIST emphasizes that securing OT must take into account performance, reliability, and security requirements. For this reason, the scope of testing should be assessed on a case-by-case basis for a given installation, rather than copying a schedule or procedure from a typical IT environment. NIST SP 800-82 Rev. 3

If there is no safe environment or approved test method, the appropriate outcome of the preparation is to describe the gap and identify the person responsible for the decision. Do not claim reproducibility that has not been verified.

Checklist Before Approving a Configuration Change

The following list outlines the preparatory discussion. It does not replace company procedures or the manufacturer's instructions.

  1. Have the device, the app, and the scope of the change been clearly defined?
  2. Is it known what the baseline condition is before starting work?
  3. Has the need to secure the program, logic, configuration, I/O, firmware, HMI files, documentation, tools, licenses, and environment image been assessed?
  4. Is every collected artifact described and linked to a specific system?
  5. Have any missing, unavailable, or unconfirmed items been recorded?
  6. Have the technical owner and the approver been identified?
  7. Is it known what level of verification was performed on the copy?
  8. Has any potential test been scheduled in a way that won't disrupt production?
  9. Does the change plan separate the creation of a copy from the decision to restore?

When Technical Consultation Is Needed

Consultation is necessary when the design and state of the device may differ, it is unclear which artifacts define the running system, specific tools are required, or the team has no secure way to verify a copy.

For the meeting, it’s a good idea to prepare a description of the change, a list of devices and applications, available projects, documentation, and open dependencies. This allows you to define the scope of artifacts and checks without promising a result that hasn’t been confirmed.

Sources